NEWTOWN TOWNSHIP SYCAMORE STREET COMMITTEE
A Reconstruction Project of Newtown Township
100 MUNICIPAL DRIVE
NEWTOWN, PA
TUESDAY, FEBRUARY 10, 2004
8:00 PM
Approval of Minutes: Mr. Nejman made a motion to approve the minutes of February 10, 2004 as presented. Mr. Tyrol seconded; the motion carried.
Members Present: Chairman Vince
Lombardi; Members Joe Merjeski, John Nejman, Frank Tyrol, Melva Vittoriano,
Michael Piazza; HARB representative Terry McLean; BOS Liaison Thomas Jirele.
Members Not Present: Rand Jaslow, Borough Liaison; David
Burns, Jr.; Barry Dinneen, Borough Representative; Shannon Wilson; Planning
Commission Liaisons Beth Sanderlin and Shawn Ward, Esq.
Also present: Nelson Shaffer
representing Pennoni Associates Inc.; Supervisors Raymond Goodnoe and Scott
Harp; John Paul Lautenschlager, Focus on Newtown - Courier Times; Robert Bebon,
Newtown Presbyterian Church; Tom McLearnon representing Chandler Hall; George
Stockburger IV; Del Purscell; John Schmidt, Advance; Milissa J. Lenahan, First
National Bank & Trust; Township Manager Robert M. Pellegrino; John Hunter,
Pennoni Associates, Inc.; Esther Lownes.
Call to Order: Chairman Lombardi
called the meeting to order at 8:04 PM.
Approval of Minutes
Mr.
Merjeski made a motion to approve the minutes of December 9, 2003 with the
following correction: change “Nelva” to
“Melva”. Mr. Tyrol seconded; the motion
carried, with abstention by Mr. McLean.
Mr. Pfeiffer said he has worked with PennDOT for over 20
years. He announced that construction
would begin on Monday; the trailer would be set up on Thursday. He said that weather is a factor, but that
they have a lot of preliminary work to do.
Mr. Pfeiffer said that temporary signs would be posted later this week,
and said that work would begin at the Richboro Road end of Sycamore
Street. He said that the CPM schedule
had been given to Pennoni for approval, and that there would be a 4-week
rolling schedule that would be updated and submitted every two weeks. Mr. Merjeski asked about signs to be posted
on site; Mr. Shaffer said they had sketches of the signage.
Mr. Lombardi said that the
website is up and running: www.sycamorestreet.org. He said that suggestions are welcome; there
is a link on the township website.
Mr. Pfeiffer clarified that
there would be a trailers on the north side of the old Acme site for Armour
Electric, H & K Group, and for PennDOT.
He said that materials would be ordered in accordance with approvals,
and that initial materials would include concrete pipe, inlets, and
manholes. Mr. Pfeiffer said the
anticipated project completion date is April 30, 2005, pushed back due to the
delayed start. Mr. Shaffer noted that
the wear coat paving needed to be done under the appropriate weather and
temperature conditions.
Mr. Pellegrino said that they
are working to tie up loose ends before the order to proceed is issued; they
have received many shop drawings and the paperwork with PennDOT has been
completed. He explained the payment
process: invoices would be given to the
engineer to sign off on, be given to him and then to the Board of
Supervisors. Payments would go through
the ECMS system, with payment authorization by Mr. Pellegrino; he is authorized
to execute payments and change orders.
Mr. Pellegrino said that the Acme lease agreement was to be approved at
the next Board of Supervisors meeting.
Mr. Shaffer announced that
John Hunter would oversee the project and communicate with Mr. Shaffer and
PennDOT. There will be a resident
inspector on the site. Mr. Shaffer said
that Pennoni would be the conduit to the township, working with Mr. Pfeiffer to
see that things go smoothly and reviewing shop drawings. He clarified that no changes would be made
without township electronic sign-off.
John Hunter presented a copy of the contractor CPM schedule. Mr. Pfeiffer explained that the schedule
shows all detailed activities and the duration of each, including start and
stop dates for each activity. Mr.
Shaffer said that he would keep the community liaison committee apprised of
what is happening, in order to keep everyone informed. There was discussion about posting
information on the website.
Mr. Pfeiffer said that in the
Richboro Road/Sycamore Street phase the utilities would be addressed first,
such as pipe, inlets, drains, and electricity behind the curb. He said the schedule might be adjusted to
complete some sidewalk work. Mr.
Lombardi noted that special attention needs to be paid to adequate access for a
handicapped resident, and asked that he be notified of anyone else on Sycamore
Street with special circumstances. Mr.
Pfeiffer said they hope to complete about 75% of construction and have things
cleared up before next winter. He said
that the schedule allows for landscaping.
Mr. Pellegrino noted that a
grant for $383,000 received by the township for streambed stabilization would
allow for some reinstallation of on-street parking; the Board of Supervisors
will look to begin the search for a contractor. He clarified that the township would receive the money up front,
with a portion allotted for engineering and the remainder for construction.
Mr. Pfeiffer said that he
would prepare a list of emergency numbers for Pennoni, and would discuss
details as they arise with representatives of Chandler Hall, which is located
in the area of initial construction. It
was clarified that construction work hours would be 8:00 pm to 5:00 am. Mr. Pfeiffer noted that one-way access
throughout construction is required under the contract. He said that concrete pipe would probably be
laid in mid-March, and that pipe trenches would be closed up when work hours
were closed. He said that the plans do
not call for any road closings. Mr.
Lombardi said that when utilities were done earlier, there were brief closings
in the early morning, which worked out because traffic was scarce at that time.
Mr. McLean noted that the
base of the streetlights should be straight, not tapered; the design had been
changed. Mr. Shaffer said he would
address the issue. The Committee agreed
that the benches would have natural finish, so as to age naturally to a silver
color; there will be approximately 30 benches installed along the length of the
street. Mr. Merjeski said he hoped that
business owners would take ownership of and maintain benches near their
establishments.
Mr. Stockburger asked what
source for construction information would be most up to date; Mr. Lombardi said
that the website would be the best resource and said he would like to see times
and locations of construction listed.
Mr. Shaffer said that the inspectors could put together a schedule. Mr. Pfeiffer said there would be a detailed
four-week rolling schedule for the township and residents to view, including
the past two and current two weeks - written in layman’s terms. Mr. Jirele suggested a weekly updated
posting of the upcoming month’s work.
Mr. Stockburger suggested posting information on cable channel 23 as
well.
It was clarified that trash
containers and traffic signals would be black.
Mr. Shaffer said he would check the lighting, suggesting that cobra head
overburden lights would probably not be necessary because of the extra
ornamental lights added.
Correspondence: None.
None.
Mr. Lombardi asked the
Community Relations subcommittee to stay for a brief meeting.
Next Meeting: The next meeting
is scheduled for March 9, 2004.
On
motion by Mr. Merjeski and without objection, the meeting was adjourned at 8:50
PM.
Respectfully
submitted,
______________________________
Leslie
P. Dunleavy, Recording Secretary